Solved

Exhibit 15 -Refer to Exhibit 15

Question 1

Short Answer

Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
 Activity  Days  Required  Predecessar  Activities  A 5B3 A  C 4 A  D 7B,CE6 C F5 E G4 D. F \begin{array} { c c c } \text { Activity } & \begin{array} { c } \text { Days } \\\text { Required } \end{array} & \begin{array} { c } \text { Predecessar } \\\text { Activities }\end{array} \\\hline \text { A } & 5 & - \\B & 3 & \text { A } \\\text { C } & 4 & \text { A } \\\text { D } & 7 & B , C \\E & 6 & \text { C } \\F & 5 & \text { E } \\G & 4 & \text { D. F }\end{array}
-Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?
 A  B  C DEFGHI1 Activity  Description  Predecessor  Time  EST  EFT  LST  LFT  Slack 2 A  Activity A 5050503 B  Activity B  A 358101354 C  Activity C  A 4595905 D  Activity D  B,C 7916132046 E  Activity E  C 691591507 F  Activity F  E 51520152008 G  Activity G  D, F 4202420240\begin{array}{|c|c|c|c|c|c|c|c|c|c|}\hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\\hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\\hline 2 & \text { A } & \text { Activity A } & & 5 & 0 & 5 & 0 & 5 & 0 \\\hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 5 & 8 & 10 & 13 & 5 \\\hline 4 & \text { C } & \text { Activity C } & \text { A } & 4 & 5 & 9 & 5 & 9 & 0 \\\hline 5 & \text { D } & \text { Activity D } & \text { B,C } & 7 & 9 & 16 & 13 & 20 & 4 \\\hline 6 & \text { E } & \text { Activity E } & \text { C } & 6 & 9 & 15 & 9 & 15 & 0 \\\hline 7 & \text { F } & \text { Activity F } & \text { E } & 5 & 15 & 20 & 15 & 20 & 0 \\\hline 8 & \text { G } & \text { Activity G } & \text { D, F } & 4 & 20 & 24 & 20 & 24 & 0 \\\hline\end{array}

Correct Answer:

verifed

Verified

Related Questions