Multiple Choice
Identify which of the statements below is not a reason why actual results would differ from those projected in the master budget.
A) Current period projected sales volume differed from the prior period projection.
B) Actual sales volume differed from projected sales volume.
C) Variable costs per unit differed from expected amounts.
D) Actual fixed costs were different than expected.
Correct Answer:

Verified
Correct Answer:
Verified