Multiple Choice
Ben Company planned to produce 12,000 units.This level of activities required 20 set-ups at a cost of $18,000 plus $500 per set-up.Actual sales were 10,000 units, requiring 15 set-ups and 12,000 machine hours.Actual set-up cost was $26,000._____ is the static budget-variance for set-ups.
A) $2,500 favorable
B) $2,500 unfavorable
C) $2,000 favorable
D) $2,000 unfavorable
Correct Answer:

Verified