The following data for the Hermit Company pertain to the produc?tion of 2,000 clay pigeons during July: Standard variable-overhead cost: $6.00 per pound of clay.
Total actual variable-overhead cost: $11,000.
Standard variable-overhead cost allowed for units produced was $12,000.
Variable-overhead efficiency variance was $240 unfavorable.
_____ is the variable-overhead flexible-budget variance.
A) $1,000 favorable
B) $240 unfavorable
C) $1,280 favorable
D) $1,000 unfavorable
Correct Answer:

Verified
Correct Answer:
Verified
Q14: An expected cost is the cost that
Q102: If the ending inventory of material is
Q103: Which of the following is a true
Q104: An example of a favorable variance is
Q106: One of the first questions a manager
Q108: Identify which of the following is not
Q109: The total flexible?budget variance can be broken
Q110: Ben Company planned to produce 12,000 units.This
Q111: Eagle Company had a favorable flexible?budget direct?material
Q112: Levels of performance that can be achieved