Multiple Choice
Which of the following is a general rule for crashing activities?
A) Crash only noncritical activities.
B) Crash activities with zero slack.
C) Crash activities with the greatest number of predecessors.
D) Crash the path with the fewest activities.
Correct Answer:

Verified
Correct Answer:
Verified