Figure 17-4 Shannon Ltd.'s Standard Cost Card Contained the Following Information

Question 77

Multiple Choice

Figure 17-4
Shannon Ltd.'s standard cost card contained the following information:
Direct labour: 1.25 hours * £8.00 per hour = £10.00
Shannon planned to make 12,000 units. Shannon actually made 10,000 units using 13,000 hours.
-Refer to Figure 17-4. Shannon's standard hours allowed for production was


A) 12,500.
B) 15,000.
C) 16,250.
D) 13,000.

Correct Answer: