Multiple Choice
Figure 17-4
Shannon Ltd.'s standard cost card contained the following information:
Direct labour: 1.25 hours * £8.00 per hour = £10.00
Shannon planned to make 12,000 units. Shannon actually made 10,000 units using 13,000 hours.
-Refer to Figure 17-4. If Shannon's actual labour cost was £136,500, Shannon's labour rate variance was
A) £32,500 unfavourable.
B) £32,500 favourable.
C) £6,500 unfavourable.
D) £6,500 favourable.
Correct Answer:

Verified
Correct Answer:
Verified
Q71: Figure 17-6 <span class="ql-formula" data-value="\begin{array}{lr}\text
Q72: Figure 17-1<br>Max Company has developed the
Q73: Figure 17-1<br>Max Company has developed the
Q74: Standard cost systems can enhance operational control
Q75: Figure 17-6 <span class="ql-formula" data-value="\begin{array}{lr}\text
Q76: Figure 17-7<br>Orient Company has developed the
Q77: Figure 17-4<br>Shannon Ltd.'s standard cost card contained
Q78: Figure 17-2<br>Rax Company has developed the
Q80: During May, 6,000 pounds of raw materials
Q81: The volume variance provides information to management