Multiple Choice
Given the following cash flows for Project M: C0 = -1,000, C1 = +200, C2 = +700, C3 =
+698, calculate the IRR for the project.
A) 23%
B) 21%
C) 19%
D) None of the above
Correct Answer:

Verified
Correct Answer:
Verified