Multiple Choice
The per-unit standards for direct labour are 3 direct labour hours at $15 per hour.If in producing 700 units, the actual direct labour cost was $31,175 for 2,150 direct labour hours worked, the total direct labour variance is
A) $50 unfavourable.
B) $325 favourable.
C) $50 favourable.
D) $325 unfavourable.
Correct Answer:

Verified