menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Management Science Quantitative Approach
  4. Exam
    Exam 9: Project Scheduling: Pertcpm
  5. Question
    Activities G,P,and R Are the Immediate Predecessors for Activity W
Solved

Activities G,P,and R Are the Immediate Predecessors for Activity W

Question 39

Question 39

Multiple Choice

Activities G,P,and R are the immediate predecessors for activity W.If the earliest finish times for the three are 12,15,and 10,then the earliest start time for W


A) is 10.
B) is 12.
C) is 15.
D) cannot be determined.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q34: A project network is shown below.Use a

Q35: Consider a project that has been modeled

Q36: For an activity with more than one

Q37: The latest finish time for an activity

Q38: The variance in the project completion time

Q40: Which of the following is always true

Q41: The project manager should monitor the progress

Q42: For the project represented below,determine the earliest

Q43: Consider the following PERT/CPM network with estimated

Q44: A project has the following activities,precedence relationships,and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines