Multiple Choice
Electric Zero produces relay units for generators.Each relay has a standard material cost of $67.Standards call for two relays per generator.In July, the company purchased 120 relays for $7,560.The company used 104 relays in the production of 50 generators, with 4 relays damaged in the installation process.The standard quantity of labor is 20 hours per generator, with a standard wage rate of $23.The company incurred 1,020 labor hours at a cost of $22,950.How much is the material quantity variance?
A) $480 favorable
B) $268 unfavorable
C) $1,340 unfavorable
D) $592 unfavorable
Correct Answer:

Verified
Correct Answer:
Verified
Q16: Why is the point of purchase the
Q17: Hanson produces pressure washers.The detail for
Q18: Ultimate Production manufactures radon detectors.The standard for
Q19: Eminem, Inc.manufactures music CDs.At the start
Q20: Billy Bob Subs has the following standard
Q22: Cuevas Company produces magic swords.It uses
Q23: Straton Company produces one product, the H2001.Each
Q24: The material quantity variance compares the actual
Q25: Electric Zero produces relay units for generators.Each
Q26: Which of the following statements is true