    ToolTime Has a Standard of 2 Hours of Labor Per
Solved

ToolTime Has a Standard of 2 Hours of Labor Per

Question 116

Question 116

Multiple Choice

ToolTime has a standard of 2 hours of labor per unit, at $12 per hour. In producing 2,000 units, ToolTime used 3,850 hours of labor at a total cost of $46,970. ToolTime's labor price variance is


A) $770 U.
B) $800 U.
C) $1,030 F.
D) $1,930 F.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q29: A two-variance approach to analyzing overhead variances

Q38: Variance analysis facilitates the principle of "management

Q60: The starting point for determining the causes

Q111: Lloyd Inc. manufactures and sells a nutrition

Q113: The standard number of hours that should

Q117: Humphreys, Inc. uses standard costing for its

Q118: Variances from standards are<br>A) expressed in total

Q119: Manufacturing overhead costs are applied to work

Q119: During March 2011, the following activity was

Q120: Newell Company developed the following standards for

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines