During March 2011, the following activity was recorded by the company relating to the production of tybos:
1. The company produced 7,500 units during the month.
2. A total of 20,000 pounds of materials were purchased at a cost of $55,000.
3. A total of 20,000 pounds of materials were used in production.
4. 4,000 hours of labor were incurred during the month at a total wage cost of $44,000.
Instructions
Calculate the following variances for March for Malone, Inc.
(a) Materials price variance
(b) Materials quantity variance
(c) Labor price variance
(d) Labor quantity variance
Correct Answer:

Verified
(a) Materials price variance
= (Actual q...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
= (Actual q...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q38: Variance analysis facilitates the principle of "management
Q60: The starting point for determining the causes
Q116: ToolTime has a standard of 2 hours
Q117: Humphreys, Inc. uses standard costing for its
Q118: Variances from standards are<br>A) expressed in total
Q119: Manufacturing overhead costs are applied to work
Q120: Newell Company developed the following standards for
Q122: Loomis Company uses both standards and budgets.
Q124: Fugate Company planned to use 1 yard
Q218: A direct labor price standard is frequently