Multiple Choice
In an assemble-to-order company, at which level should master scheduling take place?
A) the component/subassembly level
B) the end item level
C) the raw material/component level
D) it does not matter, any level will do
E) none of the above levels
Correct Answer:

Verified
Correct Answer:
Verified