Multiple Choice
The MPS is constrained by:
I. The availability of material.
II. Available capacity.
III. Inventory policies.
IV. Production plan.
A) all of the above
B) I, II, III only
C) I and II only
D) II and III only
E) none of the above
Correct Answer:

Verified
Correct Answer:
Verified