Multiple Choice
A work center consists of 2 machines working 8 hours a day and 5 days a week.
Historically, utilization has been 80% and the efficiency 90%. The effective capacity, to the nearest hour, would be:
A) 80 hours
B) 40 hours
C) 30 hours
D) 50 hours
E) 58 hours
Correct Answer:

Verified
Correct Answer:
Verified