    The Percentage of Time the Work Center Is Active Compared
Solved

The Percentage of Time the Work Center Is Active Compared

Question 4

Question 4

Multiple Choice

The percentage of time the work center is active compared to the available time is called:


A) efficiency
B) effectiveness
C) utilization
D) up-time

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: Which of the following is the best

Q2: The difference between backward scheduling and forward

Q3: A shows the capacity required at each

Q5: Rated capacity is calculated taking into account

Q6: is responsible for capacity planning at the

Q7: In one week a work center produces

Q8: Over the previous three weeks a work

Q9: A work center consists of 2 machines

Q10: is responsible for determining the capacity required

Q11: Available capacity planned to exceed capacity required

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines