Multiple Choice
?In a production scheduling LP, the demand requirement constraint for a time period takes the form
A) ?beginning inventory + production + ending inventory > demand.
B) ?beginning inventory -production + ending inventory = demand.
C) ?beginning inventory + production - ending inventory = demand.
D) ?beginning inventory - production - ending inventory > demand.
Correct Answer:

Verified
Correct Answer:
Verified