Multiple Choice
Stone Age Surfboards is a small manufacturer of two types of popular low-tide surfboards, the Graystone and the Lava models. The manufacturing process consists of two departments: fabrication and finishing. The fabrication department has 8 skilled workers, each of whom works
9.25 hours per day. The finishing department has 5 workers, each of whom works a 6-hour shift per day. Each pair of Graystone surfboards requires 2.5 labor hours in the fabrication department and 2 labor hours in finishing. The Lava model requires 4.2 labor-hours in fabrication and 3.6 labor-hours in finishing. The company operates 6 days a week. It makes a per unit profit of $40 on the Graystone model and $60 on the Lava model. The company anticipates selling at least twice as many Lava models as Graystone models.
Use the spreadsheet below for Stone Age Surfboards to answer the following questions) using integer constraints on variables in the optimization models using the standard Solver.
-What is the total number of hours used for the finishing operation?
A) 39.6
B) 34.4
C) 29.2
D) 24.8
Correct Answer:

Verified
Correct Answer:
Verified
Q37: Use the table below to answer
Q38: Use the table below to answer
Q39: Use the table below to answer
Q40: LO1: Develop and solve nonlinear optimization
Q41: Use the table below to answer
Q43: Use the table below to create
Q44: Rectilinear distance is the measure of distance
Q45: Decision variables that are forced to be
Q46: Stone Age Surfboards is a small manufacturer
Q47: Use the table below to answer