Use the Given Process Data to Construct a Control Chart 4 4 5 5 5 5 5 5 6 6 6 6 12 6 6 6 7 6 7 8 7
Essay
Use the given process data to construct a control chart for p
-A drugstore considers a wait of more than 5 minutes to be a defect. Each week 100 customers are randomly selected and timed at the checkout line. The numbers of defects for 20 consecutive weeks are given below. 4 4 5 5 5 5 5 5 6 6 6 6 12 6 6 6 7 6 7 8 7