Multiple Choice
A project consists of seven tasks labeled A through G . The table shown below gives the processing times and precedence relations. Which project digraph represents this situation?
-Consider the project above; use the priority list A, C, B, F, G, D, E to find the project finish time fin using N = 3 processors.
A) 12
B) 15
C) 14
D) 16
E) None of the above.
Correct Answer:

Verified
Correct Answer:
Verified