Multiple Choice
A company is choosing between two projects. The larger project has an initial cost of $100,000, annual cash flows of $30,000 for 5 years, and an IRR of 15.24%. The smaller project has an initial cost of $50,000, annual cash flows of $16,000 for 5 years, and an IRR of 16.63%. The projects are equally risky. Which of the following statements is CORRECT?
A) Since the smaller project has the higher IRR, the two projects' NPV profiles cannot cross, and the smaller project's NPV will be higher at all positive values of WACC.
B) Since the smaller project has the higher IRR, the two projects' NPV profiles will cross, and the larger project will look better based on the NPV at all positive values of WACC.
C) If the company uses the NPV method, it will tend to favor smaller, shorter-term projects over larger, longer-term projects, regardless of how high or low the WACC is.
D) Since the smaller project has the higher IRR but the larger project has the higher NPV at a zero discount rate, the two projects' NPV profiles will cross, and the larger project will have the higher NPV if the WACC is less than the crossover rate.
E) Since the smaller project has the higher IRR and the larger NPV at a zero discount rate, the two projects' NPV profiles will cross, and the smaller project will look better if the WACC is less than the crossover rate.
Correct Answer:

Verified
Correct Answer:
Verified
Q6: Barry Company is considering a project that
Q7: Hindelang Inc. is considering a project that
Q8: Sexton Inc. is considering Projects S and
Q10: Which of the following statements is CORRECT?<br>A)
Q13: Data Computer Systems is considering a project
Q14: Nast Inc. is considering Projects S and
Q15: Last month, Lloyd's Systems analyzed the project
Q37: The NPV and IRR methods, when used
Q42: Assuming that their NPVs based on the
Q57: Which of the following statements is CORRECT?<br>A)