A Simple Project Listing of Five Activities and Their Respective

Question 66

Multiple Choice

A simple project listing of five activities and their respective time estimates are presented below: A simple project listing of five activities and their respective time estimates are presented below:   Using CPM, which activities make up the critical path? A) A, C, D, E B) A, B, D, E C) A, C, B, D, E D) A, D, E E) None of the above Using CPM, which activities make up the critical path?


A) A, C, D, E
B) A, B, D, E
C) A, C, B, D, E
D) A, D, E
E) None of the above

Correct Answer: