Multiple Choice
Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs. If you crash this project to reduce the total time by four days, what is the total time of the project and total cost?
A) Total time is 10 days, total cost is $2500
B) Total time is 9 days, total cost is $2300
C) Total time is 8 days, total cost is $2750
D) Total time is 8 days, total cost is $1850
E) Total time is 9 days, total cost is $2350
Correct Answer:

Verified
Correct Answer:
Verified
Q36: A matrix project attempts to blend properties
Q49: The fact that organizations are flattening is
Q59: In the Time-Cost CPM model, cost is
Q59: A work breakdown structure is used in
Q61: For an activity in a CPM analysis
Q63: The second step in managing a project
Q65: A project starts out as which of
Q66: A simple project listing of five activities
Q69: Using the Time-Cost CPM model, the crash
Q72: The critical path in a CPM analysis