A Simple Project Listing of Five Activities, Their Predecessors and Their

Question 32

Multiple Choice

A simple project listing of five activities, their predecessors and their respective time estimates are presented below: A simple project listing of five activities, their predecessors and their respective time estimates are presented below:   Using CPM, what is the Latest Finish Time for the last activity in this project (i.e., the total time to complete the project) ? A) 10 days B) 7 days C) 8 days D) 12 days E) 9 days Using CPM, what is the Latest Finish Time for the last activity in this project (i.e., the total time to complete the project) ?


A) 10 days
B) 7 days
C) 8 days
D) 12 days
E) 9 days