Multiple Choice
Below are the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the costs include both direct and indirect costs. If you crash this project to reduce the total time by one day what is the total time of the project and total cost?
A) Total time is 13 days, total cost is $1500
B) Total time is 12 days, total cost is $2000
C) Total time is 12 days, total cost is $2300
D) Total time is 11 days, total cost is $1850
E) Total time is 11 days, total cost is $2350
Correct Answer:

Verified
Correct Answer:
Verified
Q5: The critical path in a project is
Q7: You have just performed a CPM analysis
Q21: You are managing a project and need
Q29: Earned Value Management (EVM) has the capability
Q31: A project can be subdivided into which
Q32: A simple project listing of five activities,
Q36: You have just been assigned to oversee
Q39: When reducing the planned duration of a
Q70: A disadvantage of a matrix project organizational
Q105: Breakthrough projects are those that provide fundamental