Solved

​A Large Drilling Machine Is Being Built to Dig a Tunnel

Question 183

Multiple Choice

​A large drilling machine is being built to dig a tunnel under a river. The drilling machine will be very big and is unlikely to be used after this project. It is being built close to the project site on the river bank. Which of the following ways of organizing a process should be used to produce the drilling machine?


A) ​Product layout
B) ​Process layout
C) ​Fixed position layout
D) ​Cellular layout

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions