    The X-Axis on a Gantt Chart Shows
Solved

The X-Axis on a Gantt Chart Shows

Question 96

Question 96

Multiple Choice

The x-axis on a Gantt chart shows?


A) Time
B) Activity name
C) Activity duration
D) Precedence relationships

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q91: PERT relies on all of the following

Q92: An activity with a slack time of

Q93: A power outage leads to computers and

Q94: The time estimate that represents the best

Q95: The use of unfamiliar software would be

Q97: In the t = (a + 4m

Q98: _ is the planning, scheduling, and controlling

Q99: A list of possible substitute workers has

Q100: The use of strong contracts with suppliers,

Q101: In a large and complex project, all

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines