Multiple Choice
An activity with a slack time of zero?
A) Is a critical path activity
B) Is a possible candidate for crashing
C) Is both a critical path activity and a possible candidate for crashing
D) Is neither a critical path activity nor a possible candidate for crashing
Correct Answer:

Verified
Correct Answer:
Verified