Solved

An Activity with a Slack Time of Zero

Question 92

Multiple Choice

An activity with a slack time of zero?


A) Is a critical path activity
B) Is a possible candidate for crashing
C) Is both a critical path activity and a possible candidate for crashing
D) Is neither a critical path activity nor a possible candidate for crashing

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions