    The Bars in a Gantt Chart Show
Solved

The Bars in a Gantt Chart Show

Question 5

Question 5

Multiple Choice

The bars in a Gantt chart show?


A) Precedence relationships
B) Activity descriptions
C) Activity start and finish times
D) Activity resources needed

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: All critical path activities have a slack

Q2: Which of the following activities would likely

Q3: When evaluating a project risk, the project

Q4: A project's critical path is the?<br>A) Longest

Q6: Poor supplier selection is an example of

Q7: An activity has a normal duration of

Q8: The longest sequence of activities in a

Q9: CPM, in a project management context, refers

Q10: Project risks that are either inside or

Q11: The fourth step in both the CPM

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines