Multiple Choice
Which of the following activities would likely be the best candidate for crashing?
A) Activity A, Slack = 14
B) Activity B, Slack = 10
C) Activity C, Slack = 0
D) Activity D, Slack = 11
Correct Answer:

Verified
Correct Answer:
Verified