Multiple Choice
If an activity has a late start time of 8 and an early start time of 10, what is the activity's slack time?
A) 2
B) 0
C) -2
D) An activity's late start time cannot be less than its early start time
Correct Answer:

Verified
Correct Answer:
Verified