Multiple Choice
Crash cost per period is determined by which of the following equations?
A) (Crash cost) / (Normal cost)
B) (Crash cost - normal cost) / (normal time - crash time)
C) (Normal time - crash time) / (crash cost - normal cost)
D) It is impossible to calculate the crash cost per period for an activity
Correct Answer:

Verified
Correct Answer:
Verified