A Project Has Four Activities

Question 22

Multiple Choice

A project has four activities. Activity A has no predecessors and a duration of 1 week. Activity B has Activity A as its predecessor and a duration of 4 weeks. Activity C has Activity A as its predecessor and a duration of 3 weeks. Activity D has activities B and C as its predecessors and a duration of 2 weeks. What is the length of critical path for this project?


A) 4
B) 5
C) 7
D) Cannot be determined from the information given