Multiple Choice
A noncritical path activity?
A) Has zero slack time
B) Contributes directly to the duration of the project
C) Has zero slack time and contributes directly to the duration of the project
D) Neither has zero slack time nor contributes directly to the duration of the project
Correct Answer:

Verified
Correct Answer:
Verified
Q15: HyperOffice is an example of a cloud-based
Q16: Modern concerns of project managers include all
Q17: A(n) _ plan is developed to assess
Q18: An activity with a slack time greater
Q19: The access to and delivery of information
Q21: A government chooses to impose new regulatory
Q22: A project has four activities. Activity A
Q23: A small printing business is considering the
Q24: The variance of the project's completion time
Q25: Activities on the critical path have slack