Solved

A Noncritical Path Activity

Question 20

Multiple Choice

A noncritical path activity?


A) Has zero slack time
B) Contributes directly to the duration of the project
C) Has zero slack time and contributes directly to the duration of the project
D) Neither has zero slack time nor contributes directly to the duration of the project

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions