Multiple Choice
If an assembly line operates for 420 minutes per day and its demand forecast calls for production of 20 units per day, what is the assembly line's takt time?
A) 420 minutes per unit
B) 20 minutes per unit
C) 21 minutes per unit
D) 0.05 minutes per units
Correct Answer:

Verified
Correct Answer:
Verified