Assume that an assembly line has three tasks that must be completed (in order, A, B, and C) . The tasks have processing times of 9, 9, and 11 minutes per unit, respectively. If the assembly line operates for 400 minutes per day with a desired output of 70 units per day, what is the takt time?


A) 13.8 units per minute
B) 5.7 units per minute
C) 0.4 units per minute
D) Cannot be determined from the information given