    In Assembly-Line Balancing, the Theoretical Minimum Number of Workstations Is
Solved

In Assembly-Line Balancing, the Theoretical Minimum Number of Workstations Is

Question 46

Question 46

True/False

In assembly-line balancing, the theoretical minimum number of workstations is found by a ratio of the sum of all task times divided by the cycle time.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q41: The first step in balancing an assembly

Q42: Using the assembly-line balancing procedure, which of

Q43: In balancing an assembly line, workstation cycle

Q44: A manufacturing cell groups the same or

Q45: A manufacturing cell layout is similar to

Q47: An assembly-line layout is similar to the

Q48: The term "assembly line" refers to progressive

Q49: The term "servicescape" refers to which of

Q50: An assembly line is also known as

Q51: The efficiency of an assembly line is

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines