A Company Must Perform a Maintenance Project Consisting of Seven

Question 28

Multiple Choice

A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here:<sub> </sub>   Using CPM, which activities make up the critical path? A)  A, B, D, F, G B)  A, C, E, F, G C)  A, C, B, F, E D)  A, D, E E)  None of these choices are correct Using CPM, which activities make up the critical path?


A) A, B, D, F, G
B) A, C, E, F, G
C) A, C, B, F, E
D) A, D, E
E) None of these choices are correct