A Project Has Four Activities: A, B, C, and D

Question 27

Multiple Choice

A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for Activity B?


A) $0 − $5K
B) $5.01K − $10K
C) $10.01K − $15K
D) $15.01K − $20K
E) Over $20K