A Company Must Perform a Maintenance Project Consisting of Seven

Question 20

Multiple Choice

A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here:<sub> </sub>   Using CPM, which activities have slack in this project? A)  A, B, C B)  B, D C)  Only C D)  C, E E)  F, G Using CPM, which activities have slack in this project?


A) A, B, C
B) B, D
C) Only C
D) C, E
E) F, G