Multiple Choice
A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: Using CPM, which activities have slack in this project?
A) A, B, C
B) B, D
C) Only C
D) C, E
E) F, G
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q15: You have just used the network planning
Q16: A project has four activities: A, B,
Q17: Pure projects suffer from duplication of resources.
Q18: In the time-cost CPM model, cost is
Q19: Which of the following is a graphic
Q21: With a pure project, team members report
Q22: Which of the following is not a
Q23: A series of projects that are organized
Q24: When reducing the planned duration of a
Q25: A project has four activities: A, B,