Multiple Choice
You have just used the network planning model and found the critical path length is 30 days and the variance of the critical path is 25 days. The probability that the project will be completed in 33 days or less is equal to (2 decimal accuracy) .
A) 0.73
B) 0.55
C) 0.12
D) 0.27
E) 0.60
Correct Answer:

Verified
Correct Answer:
Verified