Multiple Choice
In an MRP program, the program accesses the status segment of an inventory record according to specific periods called which of the following?
A) Cubed time units
B) Time buckets
C) BOM units
D) Time modules
E) Time lines
Correct Answer:

Verified
Correct Answer:
Verified