Multiple Choice
In an MRP problem, A is an MPS item. Every A requires 2 B's and 3 C's. Every B requires 5 C's. All lead times are two periods. All initial inventory values are 0. Use lot-4-lot method for order quantities for all items. If gross requirement for A is 500 in period 8, what will be the planned order release for B in period 4?
A) 0
B) 1,000
C) 500
D) 1,500
E) 6500
Correct Answer:

Verified
Correct Answer:
Verified
Q44: In this industry type, items are manufactured
Q45: A master production schedule is an input
Q46: The deeper one looks into the product
Q47: Which of the following is the net
Q48: In an MRP program, the program accesses
Q50: An output of MRP is a bill
Q51: In this industry type, Iitems are fabricated
Q52: Which of the following industry types will
Q53: The MRP program performs its analysis from
Q54: The lot-for-lot (L4L) lot-sizing technique minimizes carrying