Multiple Choice
Which of the following is the net requirement using an MRP program if the gross requirement is 1,000 and the inventory on hand is 500?
A) 1,000
B) 950
C) 500
D) 400
E) 350
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q57: A modular bill-of-materials is the term for
Q58: Which of the following is most closely
Q59: The customer grace period is a time
Q60: The economic order quantity (EOQ) lot-sizing technique
Q61: Which of the following is not a
Q63: MRP is based on dependent demand.
Q64: The least unit cost method of lot-sizing
Q65: A modular bill-of-materials includes items with fractional
Q66: In a net change MRP system, requirements
Q67: In an MRP problem, A is an