Multiple Choice
In an MRP problem, A is an MPS item. Every A requires 2 B's and 3 C's. Every B requires 5 C's. All lead times are two periods. All initial inventory values are 0. Use lot-4-lot method for order quantities for all items. What is the low level code (LLC) for B and C?
A) LLC for B is 2 and C is 1.
B) LLC for both B and C is 2.
C) LLC for B is 1 and C is 2.
D) LLC for B is 0 and C is 1.
E) LLC for all items is 1.
Correct Answer:

Verified
Correct Answer:
Verified
Q62: Which of the following is the net
Q63: MRP is based on dependent demand.
Q64: The least unit cost method of lot-sizing
Q65: A modular bill-of-materials includes items with fractional
Q66: In a net change MRP system, requirements
Q68: MRP systems seek to achieve which of
Q69: Which of the following is not a
Q70: MRP is least valuable in industries where
Q71: The three main inputs to an MRP
Q72: Which of the following is an input