Multiple Choice
Table J.5
The following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.
-Use the information in Table J.5. The average past due using the slack per remaining operations (S/RO) rule is:
A) fewer than or equal to 9.0.
B) greater than 9.0 but fewer than or equal to 18.0.
C) greater than 18.0 but fewer than or equal to 27.0.
D) greater than 27.0.
Correct Answer:

Verified
Correct Answer:
Verified