Table J.17 A Company Must Take on Seven New Projects. Each Project

Question 17

Multiple Choice

Table J.17
A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.
Table J.17 A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.    -Using the information in Table J.17 and Johnson's rule, on which day will project F be completed? A)  day 33 or earlier B)  day 33-day 36 C)  day 37-day 40 D)  day 41 or later
-Using the information in Table J.17 and Johnson's rule, on which day will project F be completed?


A) day 33 or earlier
B) day 33-day 36
C) day 37-day 40
D) day 41 or later

Correct Answer: