Multiple Choice
Table J.10
A workstation has six jobs waiting to be processed. They arrived at the end of Day 0 and it is now the beginning of Day 1. It is now time zero. Times are expressed in terms of days.
-Using the information in Table J.10 and the earliest due date (EDD) rule, which job(s) will be completed on or before their due dates?
A) F only
B) A and F only
C) B, A, and E only
D) E and B only
Correct Answer:

Verified
Correct Answer:
Verified