Multiple Choice
Table J.1
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.
-Using the information in Table J.1 and the EDD rule, what is the average flow time?
A) fewer than or equal to 25 days
B) greater than 25 days but fewer than or equal to 27 days
C) greater than 27 days but fewer than or equal to 29 days
D) greater than 29 days
Correct Answer: